Step-by-step guide

  1. Select Manage > Setup… Select Image Added General > Image Added Setup > Scheduling. The Scheduling Setup screen is displayed.
  2. Select the tab corresponding with the required task type . The (in the example below ADHOC Flightis the required task). The Default Resourcing Requirements pane  pane is displayed.
    Image Removed
    Image Added

  3. Click [Add Resource Requirement]
    Image Removed
    Image Added

  4. Enter the name of the resource in the Resource Name field. For example, Captain, First Officer, Flight Attendant, Doctor, Flight Nurse, Paramedic etc.

  5. Select the ‘Personnel’ resource type from the Type drop-down list. The resource options are updated depending on the option selected.
  6. Select the total number of this resource type required for the task type from the # Required drop-down list.

  7. Select the maximum number of this resource type required for the task type from the Max. Resources drop-down list.
    Image Removed
    Image Added

  8. Click [modify] corresponding with the Department field, to restrict the personnel resource to a particular department. If the personnel resource is not required from a specific department proceed to Step 11.
    Image Removed
  9. Enter the first characters for the required department and select the required department from the drop-down list.
    Image Removed
    Image Added

  10. Click [update] after all required department restrictions are selected.Image Removed

  11. Click [modify] corresponding with the Endorsement field, to restrict the personnel resource to a particular endorsement. If the personnel resource does not require a specific endorsement proceed to Step 14.Image Removed

     

  12. Enter the first characters for the required endorsement and select the required endorsement from the drop-down list.

    Image RemovedImage Added

     

  13. Click [update] after all required endorsement restrictions are selected.

    Image Removed

  14. Click [modify] corresponding with the Recency Requirements field, to ensure the personnel resource meets particular recency requirements. If the personnel resource does not require any specific recency requirements proceed to Step 17.

    Image Removed

     

  15. Enter the first characters for the required personnel recency item and select the required recency from the drop-down list.

    Image Removed

     Image Added

  16. Click [update] after all required recency items are selected.

    Image Removed

     

  17. Click [modify] corresponding with the Required Experience field, to restrict the personnel resource to a particular experience requirement. If the personnel resource does not require a specific endorsement proceed to Step 22.Image Removed

     

  18. Enter any character in the Required Experience drop-down list to display the applicable options.

    Image RemovedImage Added

     

  19. Select the experience requirements for this personnel resource.

    Image Removed

     Image Added

  20. Complete the minimum experience requirements in each selected field according to the options available.

    Image Removed

     Image Added

    Option

    Description

    Total Experience

    Enter the minimum total flying hours required by personnel in order to fulfil this task.

    Total Hrs. On Type

    Enter the minimum total flying hours on the associated aircraft type required by personnel in order to fulfil this task.

    Cmd. Hrs.

    Enter the minimum ‘in command’ flying hours required by personnel in order to fulfil this task.

    Cmd. Hrs. on Type

    Enter the minimum ‘in command’ flying hours on the associated aircraft type required by personnel in order to fulfil this task.

    Task Hrs. >

    Enter the minimum flying hours on the selected task (Charter, Firefighting etc.) required by personnel in order to fulfil this task. Note that the task types are configurable for each organisation via the Manage > Setup > Timesheets option and by selecting the Flight Tasks tab.

    Task Hrs. On Type

    Enter the minimum flying hours on the selected task on the associated aircraft type required by personnel in order to fulfil this task.

  21. Click [update] after all required experience restrictions are completed.

    Image Removed

     

  22. Click [Insert] to save the resource.
    Image Removed 
    Image Added


  23. Continue adding additional personnel resources to the task type by following Steps 3-22.

     

     



Filter by label (Content by label)
showLabelsfalse
max5
spacesAMKB
showSpacefalse
sortmodified
reversetrue
typepage
cqllabel in ("setting","setup","scheduling","up","personnel","requirements","resource") and type = "page" and space = "AMKB"
labelssetup setting up personnel resource requirements scheduling

 